Settlement of the asphalt surface at an operating petrol station was corrected using deep geopolymer injection. The height difference was eliminated within 5 hours, with no interruption to station operations.
Object: Dėdeliškės Petrol Station
Location: Dėdeliškės, Lithuania
Sector: Fuel Stations / Infrastructure
Technology: Deep geopolymer injection
Project: Levelling asphalt–concrete height difference; subsoil stabilisation
Product used: GEO LIFT R055
Injection depth: 1.6 m (below geogrid layer)
Duration: 5 hours
Owner: Circle K
Contractor: Geolift Baltic UAB
Engineer: Valdas Kordusas